Phased Demolition & Foundations Installation

Transformer strip-out, asbestos abatement, phased electrical installation.

Overview

Construction Savvy Ltd was appointed as Principal Contractor to manage the safe delivery of a high-risk infrastructure upgrade within a live chemical manufacturing facility. The project involved phased demolition of legacy electrical systems, asbestos abatement, and installation of new infrastructure—all while maintaining full operational continuity.

“Thanks to their professionalism and proactive approach, the project was delivered safely, on time, and with zero disruption to production operations. We had complete confidence in their leadership from start to finish.”

Dale BadgerManaging Director, Global Electrical Engineering Ltd

Global Electrical Engineering Ltd

Client: Global Electrical Engineering Ltd
Location: Prudhoe Community High School, Northumberland
Project Duration: 5 Months
Completion Date: May 2025
Role: Principal Contractor under CDM 2015

Objectives

  • Operating within a hazardous chemical environment with strict safety protocols
  • Coordinating phased works to avoid disruption to live production lines
  • Managing licensed asbestos removal and transformer decommissioning
  • Aligning multiple specialist contractors under tight programme controls

Our Approach

Martyn led the project with a structured, multi-phase delivery model designed to mitigate risk, maintain control, and ensure regulatory alignment at every stage. This approach was especially critical given the hazardous nature of the site and the need for precise coordination across disciplines.

Phase 1: Pre-Construction Planning

  • Conducted site-specific risk profiling, including hazardous material mapping and operational constraints
  • Developed a master programme with logical sequencing of demolition, abatement, and installation activities
  • Engaged stakeholders early to align expectations, access protocols, and emergency procedures
  • Produced tailored RAMS for each phase, incorporating chemical site-specific controls and contingency measures

Phase 2: Controlled Demolition & Strip-Out

  • Implemented isolation protocols and safe access routes to segregate active zones
  • Coordinated asbestos removal with licensed contractors, ensuring timely notifications and air monitoring
  • Delivered daily briefings and toolbox talks focused on phase-specific hazards and permit-to-work requirements

Phase 3: Installation & Commissioning

  • Sequenced electrical installation to align with commissioning windows and minimise interface risks
  • Monitored contractor performance using digital compliance tracking and live progress dashboards
  • Conducted phased inspections and readiness reviews prior to handover

Phase 4: Close-Out & Audit Preparation

  • Compiled evidence packs including RAMS, permits, inspection records, and contractor certifications
  • Facilitated client-side walkthroughs and documentation handover
  • Captured lessons learned to inform future phased delivery models on similar high-risk sites

Outcome

  • Project delivered safely, on time, and without disruption to chemical operations
  • Full CDM and hazardous site compliance achieved
  • Stakeholders praised clarity, professionalism, and technical oversight
  • Evidence packs retained for audit and future reference

Why Choose Us

  • Proven expertise in industrial foundation systems.
  • Precision-focused delivery under tight timelines.
  • Strong safety culture and environmental compliance.
  • Trusted by global leaders in manufacturing and materials